Sunset Strip Beautification Update


WEEKLY CONSTRUCTION UPDATE FOR FEB 23- MAR 1, 2010

Work Hours: 9:00 am – 4:00 pm, Mondays – Fridays. No weekend work.

During work hours lanes will be reduced to one travel lane in the eastbound and one travel lane in the westbound direction. At the end of the day lanes will be reopened to two lanes of traffic in each direction.

SIDEWALKS, DRIVEWAYS & CURB WORK:
This week the contractor is continuing to work on replacing damaged sidewalks, driveways, and corner ramps on both the south side of the street. Any affected driveways will be temporarily inconvenienced with steel plates installed to allow for access. A lot of the concrete work on the north side of the street has been completed. Many of the ramps at the corners have been complete.

UTILITY WORK:
Fire hydrants will be relocated to the new curb line at Sunset/King Rd and Sunset/Sweetzer Ave by LADWP.

ROADWAY REPAIRS:
This involves excavating the damaged area, fixing/compacting the soil that is under the pavement and then repaving the damaged area. The grinding of the old concrete has begun.

One lane of traffic will remain open in each direction. The roadway resumes to 2 lanes of traffic in each direction at the end of the day.

Commuters should expect delays, plan for additional time to get through the area.

All businesses will be open during their normal business hours.

Support your local businesses during construction.